Projects


 Feasibility Studies
 Completed Work
 On Going Tasks

 




Feasibility Studies
Description of major electrical systems: (EL)

a. two incoming
b. three outgoing to feed the three step-down transformers of the facility, 11/0.4 KV 1000KVA each
c. one outgoing feeder for the doctors’ residence substation transformer, 250KVA

  1. one spare cubical for future expansion
    A. The Maternity and Pediatric Hospital – Ibn Al Baladi –normally has a reliable power system. Its primary power comes from one utility substation owned by the Ministry of Electricity / Electrical Company. The facility should is fed by two feeders (11V) from two different sources (according to codes), in case of a loss of power on one of the primary lines feeding the hospital.

    B. The entire facility is backed up with emergency power from two emergency generators, which have been sized to feed the vital loads of the facility (operating theaters, emergency lighting and others).

    C. The entire facility is wired in accordance with BSI wiring standards. These wiring standards meet the majority of codes in the International Building Code.

    D. There is concern over the availability of sufficient power to operate the entire hospital, especially with the expanded volume and complexity of medical equipment to provide the medical services required of this facility. The capacities of the existing transformers, switchgear, electrical panels, distribution system and so on are as follows:
    The power distribution system consists of the following:
  2. Medium voltage switchgear (11KV)

a. It consists of seven cubicles each of 630A capacity, manually operated, as follows:
The facility has new, imported motorized circuit breaker cubicles, not installed yet, which will be a great improvement over the existing ones


3. Three step-down transformers of 1000KVA each 11KV/ 400V; the total load of the facility is divided between two transformers and the third feeds the machine room . The low tension part of each transformer is connected to a bus bar system having all the control and metering auxiliaries in addition to power factor gears. The three bus systems are connected by bus bar couplers. In case of failure of any of the transformers, their load can be handled by the others. The transformers are in good condition; only a routine test should be run to test the conductors’ insulation, chemical and electrical tests for the oil, in addition to the tests to be done to the control and monitoring devices.

4. One step-down transformer of 250KVA is installed in a separate building to feed the doctors’ residence building and its machinery room. The transformer is in good condition; only a routine test should be run to test the conductor’s insulation, and chemical and electrical tests for the oil, in addition to the test to be performed to the control and monitoring devices.


5. Two Diesel Generator sets of 810 KVA each, one in operation and the other standby. and they are designed to feed the vital loads in the facility in the event of main supply

6. The hospital has imported several high voltage breaker sets to replace damaged and
inadequate existing equipment.

7. The low voltage main distribution board, LV MDB comprises the following :
a. Two incoming feeders of 2000A circuit breakers interlocked by two 2000A generator feeders each, coupled by a 2000A circuit breaker.
b. Each of the feeders is connected to a bus bar distributing the power all over the facility. The loads are divided in a way that all the loads have power during normal supply but only the vital loads will be supplied during generator operation.
c. One 2000A feeder for the operation of the mechanical room is inter-locked with a 630A feeder from the generator to operate part of the cooling and pumps needed for the vital areas.
The switch gear equipment is operating and in good condition but, after more than twenty years of operation, one or more of these pieces of equipment, circuit breakers, relays, contactors or any other control devices could fail. The difficulty of finding genuine spare parts, even for renovation of the facility, suggests that we replace all this equipment to provide trouble free operation of the facility for the coming years and meet requirements to operate the whole service system, including the introduction of a computerized control system (building management system).

8. Uninterrupted power supply units are available in the facility to back up the most vital loads like operating theaters, delivery theaters, recovery room and anesthesia; each has its own unit and, according to maintenance staff, they are in good condition though some off them need their batteries replaced (new sets of batteries are available in their stores). In addition, the hospital had imported a new mobile, large scale UPS unit of a capacity of 750KVA; still it is a technical issue how to connect this large scale centralized unit in a properly engineered way. In addition, Siemens Corp. has provided 2 (two) generators, operating capacity 1.75MVA, which are yet to be added to the hospital systems.

9. The wiring in the facility is in good condition, conducted in an imbedded metal conduit in the walls in most areas and clipped on the walls in areas for mechanical equipment and workshops and over metal tray routes. They are as follows:
a. Lighting and power outlet installations: wiring is in good condition, in the event of facility renovation, we recommend replacement of all fittings and switches for better operation in the coming years. Due to the difficulty of obtaining required spare parts for existing fittings and introducing new types of fittings to the existing ceiling tiles, such as 60x60 cm florescent type, the entire configuration should be replaced.
b. Telephone and data system installation: replacement of all wiring is recommended with the most current type, like UTP cat5+ , also the possibility of introducing a LAN network in the same conduit system and replacing the outlets with Rj-11 type for telephones and introducing Rj-45 for a computer network
c. Other systems installation: in general, the wiring is in good condition and can be used for the new systems (nurse call, central clock, fire alarm, public address and others); each system will be discussed later and the wiring will be changed if new systems require different wiring specifications.

10. Fire alarm system: the old system consists of a central control and annunciating board sensing 39 zones all over the facility. In the event the system is replaced with a similar system in design (conventional type), there is no need to replace the wiring system; but if it is decided to implement an up-to-date system (addressable type), the new wiring system will be changed according to the new design requirement.

11. Voice and data system:
a. It is necessary to replace the existing telephone exchanger PABX with an updated system to operate a minimum 280 extensions connected to a minimum 20 public lines, with all options and accessories required for medical facilities. Accordingly, it will be necessary to replace the wiring to meet the specifications of the new digital voice and data equipment.

 

Back

Home | About Us | Alamad Structure | Elected Projects | Objectives | Who is who | Contact us


Copyright © 2004 Alamad Co. Ltd.  All Rights Reserved